Brussels planning permit timescales: 75 to 450 days

Brussels house façades under scaffolding, building site on hold

The processing timescales for a planning permit application in Brussels are set by the CoBAT (Brussels Spatial Planning Code). They vary according to the issuing authority and the assessment steps required.

How are the timescales calculated?

Article 12/1 of the CoBAT sets out the calculation rules:

The decision period runs from the date the acknowledgement of a complete application is sent. If this acknowledgement is not sent within 45 days, the period starts automatically on the 46th day.

Timescales for municipal applications

When the college of mayor and aldermen is the issuing authority (Art. 156 §2 CoBAT):

Situation Time limit
Without involvement of the delegated official and without publicity measures 75 days
With involvement of the delegated official or publicity measures 90 days
With involvement of the delegated official and publicity measures 160 days

Timescales for the delegated official

When the delegated official (urban.brussels) is the issuing authority (Art. 178 §2 CoBAT):

Situation Time limit
Without special publicity measures 75 days
With special publicity measures 160 days
With an impact study 450 days

Extensions and suspensions

Each time limit is extended by 30 days:

The time limit can also be suspended:

Completeness check

Before the decision period starts to run, the authority has 45 days to check that the application is complete. If it is incomplete, the applicant has 6 months maximum to provide the missing documents, failing which the application lapses.

After the permit is granted

Was this article helpful?

Brussels-Capital Region

Airplan is coming to Brussels soon

Airplan is not available in Brussels yet. Sign up and we will let you know as soon as it launches.